Structural Work in Van Nuys

Van Nuys sill replacement in order: temporary posts carry the wall, rotted wood comes out in sections, then new anchors and cripple-wall plywood.

Tell us about the house

By sending, you agree Aspenwell Construction may contact you by call, automated text or email about your request. Consent isn't required to buy. Msg & data rates may apply; reply STOP to opt out. Privacy Policy

A rotted sill cannot be swapped while the wall above still sits on it. In a Van Nuys crawlspace the job therefore starts with temporary posts and a cross member set just inside the foundation, snugged up under the floor joists. With the load carried, the soft wood is cut out in sections, new pressure-treated lumber goes down, and only then do anchor bolts and cripple-wall plywood follow.

Carrying the load while wood comes out

Each temporary post stands on a pad or block so it cannot sink into bare soil, and the cross member is shimmed until it just takes weight without lifting the floor. We work along the foundation one section at a time, so most of the wall always bears on sound wood. The old sill is split out, nails and bolt stubs are cut flush, and the concrete top is cleaned so the new piece sits flat. A sill gasket goes between concrete and lumber before the replacement is laid.

Bolting onto the new wood

Holes for the new anchors are drilled through the fresh sill into the concrete, and each anchor is set to the depth the plans call for, with a plate washer under its nut. Cripple wall studs are reattached, then plywood is nailed on in the pattern drawn for that wall. LADBS reviews the set before any shoring goes in, and its inspector sees anchors and nailing while they remain exposed. The temporary posts come out last, once the wall bears fully on the new sill.

About our structural work serviceEverything we do in Van Nuys

Structural Work in Van Nuys: questions

Book an inspection in Van Nuys

Describe the house and what it needs. We look at the structure first and send the quote in writing.