Inglewood whole-house remodeling done in order: frame survey, engineered plans, city permit, foundation and bolting, then new framing, systems and finishes.
An Inglewood whole-house remodel is built in the opposite direction from the way the house carries its weight. Loads run down to the footing, so the work starts there and climbs. Before any of it, we survey the existing frame, and an engineer draws the changes from it for review by the City of Inglewood. Demolition follows the permit. Then come foundation repair and bolting, new framing, rough plumbing and wiring, insulation, drywall and the finishes.
Survey and permit before demolition
Nothing is torn out until the drawings are approved, because demolition can remove the evidence the engineer needs. Our survey covers the footing, the sill plate and its bolts, the cripple walls, the floor joists and the roof framing. From it the engineer learns which walls are bearing, where repairs are due and where retrofit bolts and bracing belong. The plans then show every new beam, post and footing, and the city's plan checker reviews them. Comments come back, the drawings are revised, and only an issued permit lets the first wall come down.
Inspections that set the pace
Once the floor is open, we repair footings, replace damaged sill lumber, bolt the sill down and brace the cripple walls, and an inspector sees that work uncovered. New posts and beams rise next, each over a footing that has already passed. Plumbing, wiring and ducts are then run through the framing, and the inspector signs off on each rough system. The framing inspection comes after those approvals, because pipe and wire runs can bore or notch studs and joists. Separate checks of the insulation and the drywall nailing follow, and only then do cabinets, tile and paint arrive.
About our full home remodeling serviceEverything we do in Inglewood
Full Home Remodeling in Inglewood: questions
It depends on the load each one carries, which we read from the attic and the crawlspace. A plain partition comes out under the permit with little more than patching. A wall under ceiling joists, rafters or a beam gets a replacement header sized by the engineer, with posts down to footings that can take the weight, and the plans mark each change.
Early in the build, right after demolition. Anchor bolts and cripple-wall bracing sit at the base of the load path, and the floor is never easier to reach than when it is open. The inspector signs them off before new framing or flooring covers them, which avoids tearing into finished rooms later to reach the same sill.
It follows the load path from the bottom up. We check the foundation for cracks and settlement, look for anchor bolts in the sill, see whether the cripple walls are braced and probe the framing for rot. In the attic we trace the roof framing back to the walls that carry it. The designer and engineer plan the new layout from what we find.
Full Home Remodeling in other cities
More we build in Inglewood
Book an inspection in Inglewood
Describe the house and what it needs. We look at the structure first and send the quote in writing.